Summer projects underway across DCSD

CASTLE ROCK – While summer means a bit of a break for students, Douglas County School District staff members are hard at work on dozens of projects across the District.

The following is a list of the construction projects that are planned or underway already at our schools.

Arrowwood Elementary School

Arrowwood Elementary will receive upgrades to the automated direct digital controls and instrumentation of the mechanical system. Work will be completed with the use of District Facilities staff. The estimated completion date is August 1, 2014.

Arrowwood Elementary will also receive new carpet throughout the school. The work will be managed by Construction staff along with an Architect and Flooring Contractor. The Architect is Larson Incitti Architects and the Flooring Contractor is Next Generation Surfaces. The estimated completion date is August 1, 2014.

 

Castle Rock Middle School

Castle Rock Middle School will have the flooring in the restrooms replaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor is Next Generation Surfaces. The estimated completion date is August 1, 2014.

 

Castle Rock Middle School will also have the domestic hot water system upgraded. The work will be managed by Facilities staff. The estimated completion date is August 1, 2014.

 

Castle View High School

Castle View High School is remodeling some of its space for the Mosiac program. LKA is the architect contractor.

Castle View will also recieve a new mobile. This project is being coordinated by the Facilities staff.

Chaparral High School

Chaparral High School will receive a new track surface. The work will be managed by Construction staff along with an Architect and Track Contractor. The Architect is DLH Architects and the Track Contractor is Renner Sports Surfaces. The estimated completion date is August 1, 2014.

Chaparral High School will also have the intercom and paging system replaced. The work will be managed by Construction staff along with an Electrical Engineer and Communications Contractor. The Electrical Engineer is BCER Group and the Communications Contractor is Beacon Communications. The estimated completion date is August 1, 2014.

Finally, Chaparral is having some work done to its Security Kiosk. The work will be managed by the Facilities staff and contractor Danish Craftsman. The estimated completion date is June 20, 2014.

Cherokee Trail Elementary School

Cherokee Trail Elementary will have the tartan floor in the gymnasium re-surfaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor for the tartan floor is Ponder Company. The estimated completion date is August 1, 2014.

Douglas County High School

Douglas County High School will have the main electrical switchgear and panelboards replaced. The work will be managed by Construction staff along with an Electrical Consultant and Electrical Contractor. The Electrical Consultant is JSH Associates and the Electrical Contractor is ADK Electric. The estimated completion date is August 1, 2014.

Douglas County High School Stadium will have the roof replaced on the Locker Room Building. The work will be managed by Facilities staff and a Roofing Contractor. The estimated completion date is August 1, 2014.

Eagle Ridge Elementary School

Eagle Ridge Elementary will have the cafeteria flooring replaced and will have the floor in the gymnasium re-surfaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor for the cafeteria flooring is Next Generation Surfaces and the Flooring Contractor for the tartan floors is Ponder Company. The estimated completion date is August 1, 2014.

Franktown Elementary School

Franktown Elementary will have the floor in the gymnasium re-surfaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor is Ponder Company. The estimated completion date is August 1, 2014.

Highlands Ranch High School

Highlands Ranch High School will receive a new track surface. The work will be managed by Construction staff along with an Architect and Track Contractor. The Architect is LKA Partners and the Track Contractor is Renner Sports Surfaces. The estimated completion date is August 1, 2014.

Highlands Ranch High School will have the intercom and paging system replaced. The work will be managed by Construction staff along with an Electrical Engineer and Communications Contractor. The Electrical Engineer is BCER Group and the Communications Contractor is Beacon Communications. The estimated completion date is August 1, 2014.

Highlands Ranch High School will receive asphalt repairs to the parking lot. The work will be managed by Facilities staff and an Asphalt Contractor. The Asphalt Contractor will bid for the project. The estimated completion date is August 1, 2014.

Highlands Ranch High School will also receive new roofing over a small section of the school. The work will be managed by Construction staff along with a Roofing Consultant and Roofing Contractor. The Roofing Consultant is Foothills Roofing and the Roofing Contractor is Turner Morris. The estimated completion date is August 1, 2014.

Finally, Highlands Ranch is having some work done to its Security Kiosk. The work will be managed by the Facilities staff and contractor Danish Craftsman. The estimated completion date is June 13, 2014.
 

Joint Service Center

The Joint Service Center will have a section of the roof replaced and two sections will be restored.The work will be managed by Facilities staff along with a Roofing Contractor. The Roofing Contractor will bid for the work. The estimated completion date is August 1, 2014.

Ironhorse Elementary School

Ironhorse Elementary will receive an upgrade to the entire fire alarm system, including a new panel, wiring and devices. The work will be managed by Construction staff along with an Electrical Engineer and an Electrical Contractor. The Electrical Engineer is CEI and the Electrical Contractor is Allied Power Services. The estimated completion date is August 1, 2014.

 

Ironhorse Elementary will have the playpad converted from asphalt to concrete. The work will be managed by Facilities staff along with a Concrete Contractor. The Concrete Contractor will bid for the project. The estimated completion date is August 1, 2014.

 

Legend High School

Legend High School is having a DECA Store created. The work will be managed by the Facilities staff. LKA is the architect contractor.

Legend is also getting a new mobile and this project is being managed by the Facilities staff.

Library Media Center

The Library Media Center will be undergoing work on its HVAC system this summer. Work is being managed by the Facilities staff and contractor W.O. Daneilson. The estimated completion date is July 25, 2014.

Meadow View Elementary School

Meadow View Elementary will receive new carpet throughout the school. The work will be managed by Construction staff along with an Architect and Flooring Contractor. The Architect is Larson Incitti Architects and the Flooring Contractor is Next Generation Surfaces. The estimated completion date is August 1, 2014.

Mountain View Elementary School

Mountain View Elementary will have the kitchen flooring replaced along with the flooring in the gymnasium. The work will be managed by Construction staff along with an Architect and General Contractor. The Architect is Burkett Design and the General Contractor is W.O. Danielson Construction. The estimated completion date is August 1, 2014.

Mountain Vista High School

Mountain Vista High School will receive a new track surface. The work will be managed by Construction staff along with an Architect and Track Contractor. The Architect is DLH Architects and the Track Contractor is General Acrylics. The estimated completion date is August 1, 2014.

Mountain Vista High School will also have the intercom and paging system replaced and will have the fire alarm system upgraded. This work will be managed by Construction staff along with an Electrical Engineer, Electrical Contractor and Communications Contractor. The Electrical Engineer is BCER Group, the Electrical Contractor is St. Andrews Construction Services, and the Communications Contractor is Beacon Communications. The estimated completion date is August 1, 2014.

Mountain Vista is also having a STEM Lab built over the summer and is remodeling its Training Room door. This work will be managed by the Facilities staff. Yon Tanner Architecture is the architect on the STEM Lab and LKA is the architect on the Training Room.

Northridge Elementary School

Northridge Elementary will have the cafeteria flooring replaced and will have the floor in the gymnasium re-surfaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor for the cafeteria flooring is Next Generation Surfaces and the Flooring Contractor for the gymnasium is Ponder Company. The estimated completion date is August 1, 2014.

Pine Lane Elementary School

Pine Lane Intermediate will receive new carpet throughout the school. The work will be managed by Construction staff along with an Architect and Flooring Contractor. The Architect is Larson Incitti Architects and the Flooring Contractor is Cody Flooring & Tile. The estimated completion date is August 1, 2014.

Pine Lane is also having a new marquee signage added at the school. The work will be managed by the Facilities staff along with the contractor YESCO. The estimated completion date is July 25, 2014.

Pioneer Elementary School

Pioneer Elementary will receive a new roof. The work will be managed by Construction staff along with a Roofing Consultant and Roofing Contractor. The Roofing Consultant is Cave Consulting and the Roofing Contractor is WeatherSure Systems. The estimated completion date is August 1, 2014.

Pioneer Elementary will have the flooring in two restrooms replaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor is Next Generation Surfaces. The estimated completion date is August 1, 2014.

Pioneer Elementary will also receive an upgrade to the entire fire alarm system, including a new panel, wiring and devices. The work will be managed by Construction staff along with an Electrical Consultant and Fire Alarm Contractor. The Electrical Consultant is Consulting Engineers, Inc. and the Fire Alarm Contractor is Simplex Grinnell. The estimated completion date is August 1, 2014.

Ponderosa High School

Ponderosa High School will have the synthetic turf field replaced. The work will be managed by Construction staff along with an Architect and Turf Contractor. The Architect is LKA Partners and the Turf Contractor is Academy Sports Turf. The estimated completion date is August 1, 2014.

 

Ponderosa High School will also have the Auto Shop expanded. The work will be managed by Facilities along with an Architect and General Contractor. The Architect is LKA Partners and the General Contractor will bid for the work. The estimated completion date is August 1, 2014.

 

Ranch View Middle School

Ranch View Middle School will have the domestic hot water system upgraded. The work will be managed by Facilities staff. The estimated completion date is August 1, 2014.

Rock Canyon High School

Rock Canyon High School will have the synthetic turf field replaced. The work will be managed by Construction staff along with an Architect and Turf Contractor. The Architect is DLH Architecture and the Turf Contractor is Academy Sports Turf. The estimated completion date is August 1, 2014.

Rock Canyon High School will also have the intercom and paging system replaced. The work will be managed by Construction staff along with an Electrical Engineer and Communications Contractor. The Electrical Engineer is BCER Group and the Communications Contractor is Beacon Communications. The estimated completion date is August 1, 2014.

Rock Canyon is also having some of its computer labs turned into classrooms. The work will be managed by Facilities staff along with the contractor W.O. Daneilson. The estimated completion date is June 27, 2014.

Finally, Rock Canyon is having some work done to its Security Kiosk. The work will be managed by the Facilities staff and contractor Danish Craftsman. The estimated completion date is June 20, 2014.

Rocky Heights Middle School

Rocky Heights Middle School will have its Media/Arts room remodeled. Facilities will be managing the project. The contractor is HS Designbuild. The estimated completion date is July 25, 2014.

Roxborough Intermediate School

Roxborough Intermediate School is having work done on its flooring. The work will be managed by the Facilities staff. The estimated completion date is July 18, 2014.

Saddle Ranch Elementary School

Saddle Ranch Elementary will have the parking lot, bus loop and play pads resurfaced. Selected curb and gutter will also be replaced. The work will be managed by Facilities staff and an Asphalt Contractor. The Asphalt Contractor will bid for the project. The estimated completion date is August 1, 2014.

Sand Creek Elementary School

Sand Creek Elementary will have the cafeteria flooring replaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor is Next Generation Surfaces. The estimated completion date is August 1, 2014.

Sedalia Elementary School

Sedalia Elementary will receive an upgrade to the entire fire alarm system, including a new panel, wiring and devices. The work will be managed by Construction staff along with an Electrical Engineer and Electrical Contractor. The Electrical Engineer is CEI and the Electrical Contractor is Allied Power Services. The estimated completion date is August 1, 2014.

Sedalia Elementary will also have the floor in the cafeteria re-surfaced. This project will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor is Ponder Company. The estimated completion date is August 1, 2014.

Sierra Middle School

Sierra Middle School will receive an upgrade to the water well system components, including tanks, pumps and lines. The work will be completed with the use of District Facilities staff. The estimated completion date is August 1, 2014.

Sierra Middle School will have the floor in the gymnasium re-surfaced. This project will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor is Ponder Company. The estimated completion date is August 1, 2014.

Sierra Middle School will also have the domestic hot water system upgraded. The work will be managed by Facilities staff. The estimated completion date is August 1, 2014.

South Ridge Elementary School

South Ridge Elementary will have the floor in the gymnasium re-surfaced. This project will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor is Ponder Company. The estimated completion date is August 1, 2014.

Summit View Elementary

Summit View Elementary will have the cafeteria flooring replaced and will have the tartan floor in the gymnasium re-surfaced. The work will be managed by Construction and Facilities staff along with a Flooring Contractor. The Flooring Contractor for the cafeteria flooring is Next Generation. Surfaces and the Flooring Contractor for the tartan floor is Ponder Company. The estimated completion date is August 1, 2014.

ThunderRidge High School

ThunderRidge High School will receive a partial roof replacement, the intercom and paging system will be replaced, skylights will be replaced in the gymnasium, and the fire alarm system will be upgraded. The work will be managed by Construction staff along with an Electrical Engineer, Roofing Consultant, Electrical Contractor, Communications Contractor and Roofing Contractor. The Electrical Engineer is Rondinelli/BCER Group, the Roofing Consultant is SR-dK, the Electrical Contractor is St. Andrews Construction Services, the Communications Contractor is Beacon Communications, and the Roofing Contractor is Turner Morris. The estimated completion date is August 1, 2014.

ThunderRidge High School will receive asphalt repairs to the parking lot. The work will be managed by Facilities staff and an Asphalt Contractor. The Asphalt Contractor will bid for the project. The estimated completion date is August 1, 2014.

ThunderRidge High School will have energy and water saving equipment installed as part of an Energy Performance Contract. The work will be managed by Construction staff and an Energy Services Contractor. The Energy Services Contractor is McKinstry. The estimated completion date is August 1, 2014.

Finally, ThunderRidge is also having a second Security Kiosk built. The work will be managed by the Facilities staff and contractor Danish Craftsman. The estimated completion date is July 4, 2014.

Wilcox Administration Building

Wilcox Administration Building will have energy and water saving equipment installed as part of an Energy Performance Contract. The work will be managed by Construction staff and an Energy Services Contractor. The Energy Services Contractor is McKinstry. The estimated completion date is August 1, 2014.

Misc. Projects

Caulking and weatherproofing will be assessed at all schools. The work will be managed and performed by Facilities staff. The estimated completion date is August 1, 2014. 

Entry intercom systems at various middle schools will be upgraded. The work will be managed by District Security staff. The estimated completion date is August 1, 2014. 

Exterior doors and frames will be replaced at various schools. The work will be managed by Facilities staff. The estimated completion date is August 1, 2014.

Field and track repairs will be made district wide. The work will be completed with the use of District Facilities staff. The estimated completion date is August 1, 2014. 

Five to six mobile classrooms will receive new carpet. The locations are to be determined. The work will be managed by Construction staff along with an Architect and Flooring Contractor. The Flooring Contractor will bid for the project. The estimated completion date is August 1, 2014. 

Lighting and mechanical controls will be upgraded at eleven schools. This work will be managed by Construction and an Energy Services Contractor. The Energy Services Contractor is McKinstry. The estimated completion date is August 1, 2014.

Magnetic door releases will be added in specific locations in all Middle Schools and emergency notification buttons will be added in all High Schools. This work will be managed by Facilities staff. The estimated completion date is August 1, 2014. 

June 3, 2014 | By rmbarber | Category:

District News

kids running outside as part of a race

DCSD is requesting parent input on the health and wellness of our students. Last year, DCSD received a large planning grant from Colorado Health Foundation in an effort to assess how the district supports students through the lens of the Whole School, Whole Community, Whole Child model (WSCC). The mission of this grant is to review the current state of DCSD's student health and wellness program, and then formulate a three to five-year plan based on stakeholders’ needs, the latest research, and best practices. As part of this process, we would like your input.

How are we doing?

We want to hear from you! How often do you prefer to receive email newsletters from DCSD? How can we improve the news and information you receive? This brief survey should only take a minute or two of your time. Thank you for giving us your input!

Tell us what you think, here!

 

glowing purple lights hover over trays of seedlings in a dark room

It may look like a plain, white shipping container was just parked on the backyard grounds of Mountain Vista High School. The contents of the container are anything but plain, though. Walking inside the container, different colors of ambient lighting glow, futuristic-looking equipment and tall towers are suspended from the ceiling, and the humidity level is set to 70 percent. The container has been recycled into a new kind of learning opportunity for students.